KITCHEN Renovation and Extension Estimates

Renovation of Kitchen, Extension and Swimming Pool

Project Description:

  1. Spandrel dirty kitchen ( 2ft x 23ft), gutter, down spout, flashing and demolition—Php 26,000
  2. Spandrel and flashing (182cm x 300 cm) in front of sliding door—17,000
  3. Spanderl Pasilyo ( 172 cm x 1170 cm) and demolition and electrical—-48,000
  4. Spandel garage ( 308 cm x 526 cm) and demolition——-43,000
  5. Swimming pool ( 3m x 4.4m ) —— 180,000

Note: Painting, granite , tiles are excluded

TOTAL CONTRACT COST: Php 340,000.00

Scope of Works:

  1. Mobilization
  2. Demolition
  3. Layout and excavation
  4. Masonry and Concrete Works
  5. Carpentry Works
  6. Electrical Works
  7. Steel works
  8. Roofing works
  9. Plumbing Works
  10. Housekeeping
  11. Hauling of materials

Proposed Kitchen and Dining Renovation and Proposed Store Estimates

Project Name: Proposed Kitchen and Dining Renovation and Proposed Store

Location: Barrio Luz, Kitang 2, Limay, Bataan

Job Description:

• Kitchen Renovation with island counter
• Dining Renovation
• Store with roll up and grills, 2 sliding windows, 1 door for exit
• Backfilling for store

Scope of Works:

  1. Hauling of materials
  2. Demolition of old kitchen
  3. Masonry and Concrete Works
  4. Tileworks
  5. Carpentry Works
  6. Electrical Works
  7. Plumbing Works
  8. Painting Works
  9. Housekeeping

Material Specification:

• Rib type for roofing
• Stainless gutter 304
• Bubbles Insulation included
• Metal furring and hardiflex for ceiling
• Granite flooring for flooring and kitchen
• Pin lights for Dining Area and LED lights for kitchen
• Boysen Paint

Labor

• 2 Mason and 3 helpers
• Electrician and helper
• Plumber
• Driver for service vehicle
• Carpenter and helper
• Welder
• Painter and helper

Total Project Cost ———————————Php 744,000.00