Sample Construction Progress Report

PROGRESS REPORT No. 1

Project Name: One-Storey Residential House (Bungalow)
Location: Lot 12 Blk 5 Cholo Village, Sta. Cruz, Laguna
Owner: Mr. and Mrs. Eduardo L. Manzano

PROJECT SUMMARY
(Oct – Nov. 3, 2015)

• Material Mobilization
• Barrack Formation
• Site Clearing and Layout (Site Preparation)
• Site Excavation
• Formation of Steel Column and foundation footing
• Pouring of concrete forms and foundation wall
• Erection of Steel Column
• Wall footing
• Filling of CHB
• Steel Framing
• Formation of Tie Beam
• Pouring of Tie Beam
• Filling of CHB for wall and window and door formation

WORK ANTICIPATED
(Nov. – Dec. 2015)

• Pouring of Concrete Column
• Filling of CHB for wall, windows and door
• Formation of Roof Beam and Reinforcement
• Pouring of Concrete in Roof Beam
• Steel Trusses formation
• Wall Plastering

 

CHANGE ORDER

Additional Work :
• Revision of storage room and common comfort room
• 4 sqm extension with tie beam and extension of walls
• Additional windows and door

Cost: Php 60,000.00

PROJECT COST SUMMARY:

Billing Information

Original Contract Amount : Php 2,500,000.00
Changes to Contract: 60,000.00
Current Contract Amount: 2,560,000.00
Previous Billed Amount: 500,000.00
Previous Balance Remaining: 2,060,000.00
Current Payment Due (20%) 500,000.00
Remaining Balance: 1,560,000.00

Prepared by:

Engr. Jcmer M. Herrera
Project Engineer