PROGRESS REPORT No. 1
Project Name: One-Storey Residential House (Bungalow)
Location: Lot 12 Blk 5 Cholo Village, Sta. Cruz, Laguna
Owner: Mr. and Mrs. Eduardo L. Manzano
PROJECT SUMMARY
(Oct – Nov. 3, 2015)
• Material Mobilization
• Barrack Formation
• Site Clearing and Layout (Site Preparation)
• Site Excavation
• Formation of Steel Column and foundation footing
• Pouring of concrete forms and foundation wall
• Erection of Steel Column
• Wall footing
• Filling of CHB
• Steel Framing
• Formation of Tie Beam
• Pouring of Tie Beam
• Filling of CHB for wall and window and door formation
WORK ANTICIPATED
(Nov. – Dec. 2015)
• Pouring of Concrete Column
• Filling of CHB for wall, windows and door
• Formation of Roof Beam and Reinforcement
• Pouring of Concrete in Roof Beam
• Steel Trusses formation
• Wall Plastering
CHANGE ORDER
Additional Work :
• Revision of storage room and common comfort room
• 4 sqm extension with tie beam and extension of walls
• Additional windows and door
Cost: Php 60,000.00
PROJECT COST SUMMARY:
Billing Information
Original Contract Amount : Php 2,500,000.00
Changes to Contract: 60,000.00
Current Contract Amount: 2,560,000.00
Previous Billed Amount: 500,000.00
Previous Balance Remaining: 2,060,000.00
Current Payment Due (20%) 500,000.00
Remaining Balance: 1,560,000.00
Prepared by:
Engr. Jcmer M. Herrera